Recently, there has been an increasing number of cases of improving constructability by using electronic detonators with precise delay time in tunnel blasting sites. This case is a case of conducting test blasting using with non-electric detonator and electronic detonator at the site of 『Seoul Metropolitan Area Express Railroad Route A Private Investment Project Section 00』 that requires careful management of vibration and noise. Although this site was designed with a non-electric detonator, it was attempted to improve the advance rate and control vibration and noise by mixing the non-electric detonator and the electronic detonator due to the decrease in the advance rate. As a result of the blasting, the target value was achieved with an advance rate of about 85% and a maximum measured value of vibration and noise is 0.215cm/sec and 73.22dB(A) which were measured below regulatory standards. As blasting works in downtown areas, it is necessary to designate measurement and management objects to continuously manage vibration and noise.