To establish and vitalize a public building’s pre-architectural planning, this study intends to derive specific analysis items, determine the current status and navigate system improvements. The pre-architectural planning analysis items were prepared by comparing and analyzing the 'Pre-architectural Planning Task Performance Guideline' items and the preliminary review items; a total of 346 actual public building projects were analyzed. On average, 45.69% of 68 items were performed, however, details on materializing public characteristics, improving the class and design details regarding the project management systems were insufficient. As a result of conducting a one-way ANOVA on the use of buildings, institutions, and construction methods, it was found that the ordering institutions and construction methods had an impact on the current status of construction planning. The correlation according to the size of the design cost was judged to be minimal. Therefore, a plan to differentiate planning work based on these institutions and construction methods including subdividing the system improvement direction items were proposed.
본 연구는 건축기획업무 제도의 정착 및 활성화를 위해 현황을 진단하고 개선 방향을 모색하고자 함. 분석 대상은 2020년 346건의 실제 사업으로 하였으며 68개의 전체 항목을 평균적으로 45.69% 수행하였으며 공공성 구현 및 품격 제고에 관한 사항과 디자인 및 사업 관리 체계에 관한 사항에 대한 수행이 전반적으로 미흡함. 건축물용도, 발주기관, 건립방식, 설계비규모 변수 간 일원분산분석(ANOVA) 및 회귀분석을 실시한 결과를 바탕으로 항목에 대한 구체화를 비롯하여 발주기관 및 건립방식에 따른 기획업무 차별화 방안을 제안함.