成宜高铁天府站枢纽牵引变配电所是 220 kV牵引变电所和110/10 kV变配电所合建所.所内高低压电缆众多,为合理布置电缆,方便电缆运维,采用BIM技术对所内高压电缆的布置进行辅助设计,优化电缆敷设路径.
The traction transformer and distribution station of Tianfu Station of Chengyi High-speed Railway is a joint construction institute of 220 kV traction substation and 110/10 kV transformer and distribution substation.There are many high and low voltage cables in the station.In order to reasonably arrange cables and facilitate cable operation and maintenance,BIM technology is adopted to auxiliary design the layout of high voltage cables in the station and optimize the cable laying path.